What is the present worth of a safety improvement benefit of $5,000 set to occur in 5 years at an interest rate of 4%?

Prepare for the Professional Traffic Operations Engineer Exam. Study with flashcards and multiple choice questions, gain insights with hints and explanations. Ace your PTOE exam!

To determine the present worth of a future benefit, you need to calculate the present value (PV) of that future amount using the formula for present value:

[ PV = \frac{FV}{(1 + r)^n} ]

where:

  • ( FV ) is the future value (in this case, the safety improvement benefit of $5,000),

  • ( r ) is the interest rate (0.04 for 4%),

  • ( n ) is the number of years until the benefit is realized (5 years).

Plugging the values into the formula, we have:

[ PV = \frac{5000}{(1 + 0.04)^5} ]

Calculating the denominator:

[ (1 + 0.04)^5 = 1.04^5 \approx 1.2167 ]

Now substituting back into the present value formula gives:

[ PV \approx \frac{5000}{1.2167} \approx 4,110.62 ]

So, the present worth of the safety improvement benefit is approximately $4,110.62, which when rounded is $4,110. This calculation accurately reflects how the time value of money affects the